Work Plan - Work Package 4
Plant operation monitoring and testing, Analyses and Environmental impact assessment
WP4 is led by
The Work Package tasks are the followings:
- 1. Analysis of raw material (fish, waste components etc), in close co-operation with VTT
- 2. Monitoring and testing of energy balances and material flows of all subsystems in close co-operation with RCEE and AFI. AFI and RCEE will perform the measurements under the guidance of TÜV.
- 3. Environmental impact assessment of the operational plant.
The expected results are:
- D8. Public Report: Raw material analysis
- D9. Confidential Report : Test results of trial runs
- D10. Public Report: Environmental impact assessment